Time: On December 22, 2025.
Location: Congo.
Event: On December 22, 2025. CORINMAC's 5TPH(ton per hour) dry mortar production line with sand drying production line was successfully loaded and shipped to Congo.
The whole set of 5TPH dry mortar production line equipment including ton bag un-loader, screw conveyor, weighing hopper, manual feeder for chemical additives, single shaft paddle mixer, steel structure, finished product hopper, impeller packing machine for valve bag, PLC control cabinet, air compressor and spare parts, etc.
The whole set of sand drying production line equipment including 5T wet sand hopper, belt feeder, belt conveyor, three-circuit rotary dryer, burning chamber, burner, vibrating screen, steel structure, draught fan, cyclone dust collector, impulse bags dust collector, control cabinet and spare parts, etc.
Container loading photos are as follows:
Post time: Dec-23-2025